12 men can do a work in X days. 20 women can do the same work in (X -1) days. 15 men can do the work in y days while 30 women can do it (Y- 2) days . Find the value of X.
5 3005 5e8ffa0290613f3f9422d168
Q:
12 men can do a work in X days. 20 women can do the same work in (X -1) days. 15 men can do the work in y days while 30 women can do it (Y- 2) days . Find the value of X.
- 18false
- 210true
- 312false
- 415false
- 516false
- Show Answer
- Workspace
- Discuss