12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work?
5 1455 5dbfba79656bc31fa3165069
Q:
12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work?
- 110 daysfalse
- 212 daysfalse
- 315 daysfalse
- 49 daystrue
- Show Answer
- Workspace
- Discuss