Get Started
820

Q:

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped on the second day, four more workers dropped on third day and so on. It takes 8 more days to finish the work now, find the number of days in which the work was completed?

  • 1
    28
  • 2
    24
  • 3
    25
  • 4
    30
  • Show Answer
  • Workspace

Answer : 3. "25"

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today