20 men could complete a work in 80 days. They worked together for 60 days, after that due to bad whether the work is stopped for 10 days. How many more men should be employed so as to complete the work in time?
5 2986 60a7a3f4eb4d147142bf203b
Q:
20 men could complete a work in 80 days. They worked together for 60 days, after that due to bad whether the work is stopped for 10 days. How many more men should be employed so as to complete the work in time?
- 115false
- 220true
- 312false
- 410false
- Show Answer
- Workspace
- Discuss