Get Started
1124

Q:

40 men can complete a piece of work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in 

  • 1
    $$ 56{2\over 3} days $$
  • 2
    $$ 53{1\over 3} days $$
  • 3
    52 days
  • 4
    50 days
  • Show Answer
  • Workspace

Answer : 1. "$$ 56{2\over 3} days $$"

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today