40 men can complete a piece of work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
5 1133 5dd62ac4c2282c484e4b3a66
Q:
40 men can complete a piece of work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
- 1$$ 56{2\over 3} days $$true
- 2$$ 53{1\over 3} days $$false
- 352 daysfalse
- 450 daysfalse
- Show Answer
- Workspace
- Discuss