45 men can complete a work in 16 days, 6 days after they started working. 30 more men join them. How many days will they now take to complete the remaining work?5
1217 5bdc57ae0da81e269593b6d6
Q: 45 men can complete a work in 16 days, 6 days after they started working. 30 more men join them. How many days will they now take to complete the remaining work?
- 14false
- 25false
- 36true
- 48false
- Show Answer
- Workspace
- Discuss