Get Started
1354

Q:

8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed? 

  • 1
    4 days
  • 2
    5 days
  • 3
    2 days
  • 4
    3 days
  • Show Answer
  • Workspace

Answer : 1. "4 days "

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today