A's 2 days work is equal to B's 3 days work. If A can complete the work in 8 days, then to complete the work B will take:
5 962 5f4ce807081699374e81fa35
Q:
A's 2 days work is equal to B's 3 days work. If A can complete the work in 8 days, then to complete the work B will take:
- 116 daysfalse
- 214 daysfalse
- 315 daysfalse
- 412 daystrue