A and B can do a piece of work in 20 days and 30 days respectively. They started the work together but after 8 days they doing work in alternate days, started with B. how many days the work will be completed?
5 2135 5e9da3acef7e02504892dc5a
Q:
A and B can do a piece of work in 20 days and 30 days respectively. They started the work together but after 8 days they doing work in alternate days, started with B. how many days the work will be completed?
- 120false
- 212false
- 314false
- 416true
- 58false
- Show Answer