A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in
5 844 5ec5f083980ff60a66c356f2
Q:
A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in
- 15 daysfalse
- 2$$ 5{1\over3}$$ daystrue
- 38 daysfalse
- 410 daysfalse
- Show Answer
- Workspace
- Discuss