A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves , B continues for 2 more days , and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work?
5 1079 5ed9bcd9e11a1c4b43e63407
Q:
A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves , B continues for 2 more days , and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work?
- 15 daysfalse
- 28 daysfalse
- 33 daysfalse
- 44 daystrue
- Show Answer
- Workspace
- Discuss