A and B together can complete a piece of work in 3 days. They start together. But, after 2 days, B left the work, if the work is completed after 2 next days. B alone could do the work in

  • 1
    10 days
  • 2
    4 days
  • 3
    6 days
  • 4
    8 days
  • Show Answer
  • Workspace

Answer : 3. "6 days"