Get Started
1130

Q:

A and B together can do a piece of work in 12 days which B and C together can do in 16 days. After A has been working at it for 5 days and B for 19 days, C finishes it in 7 days. In how many days B could finish the whole work? 

  • 1
    48 days
  • 2
    24 days
  • 3
    16 days
  • 4
    12 day
  • Show Answer
  • Workspace

Answer : 1. "48 days "

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today