Get Started
822

Q:

A and B together can do a piece of work in 16 days and B and C together can do the same work in 24 days. From starting A and B worked for 4 days and 7 days respectively, when A lefts the work then C joins the work and he works for 23 days and complete the work. Then find in how many days will C complete the work alone?

  • 1
    32 days
  • 2
    72 days
  • 3
    16 days
  • 4
    8 days
  • Show Answer
  • Workspace

Answer : 1. "32 days "

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today