A and B together can do a piece of work in 16 days and B and C together can do the same work in 24 days. From starting A and B worked for 4 days and 7 days respectively, when A lefts the work then C joins the work and he works for 23 days and complete the work. Then find in how many days will C complete the work alone?
5 844 614dba6b9029102b5bc61a38
Q:
A and B together can do a piece of work in 16 days and B and C together can do the same work in 24 days. From starting A and B worked for 4 days and 7 days respectively, when A lefts the work then C joins the work and he works for 23 days and complete the work. Then find in how many days will C complete the work alone?
- 132 daystrue
- 272 daysfalse
- 316 daysfalse
- 48 daysfalse
- Show Answer
- Workspace
- Discuss