A, B and C can complete a piece of work in 10, 12, and 15 days respectively, They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
5 1165 5d71f0d9e70d464ce7165103
Q:
A, B and C can complete a piece of work in 10, 12, and 15 days respectively, They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
- 14 daysfalse
- 25 daysfalse
- 37 daystrue
- 48 daysfalse
- Show Answer
- Workspace
- Discuss