A can complete a piece of work in 10 days, B in 15 days and C in 20 days, A and C worked together for two days and then A was replaced by B. In how many days, altogether, work was completed?
5 897 5ee1f6a92bf4c40446469c7d
Q:
A can complete a piece of work in 10 days, B in 15 days and C in 20 days, A and C worked together for two days and then A was replaced by B. In how many days, altogether, work was completed?
- 112 daysfalse
- 210 daysfalse
- 36 daysfalse
- 48 daystrue
- Show Answer