Get Started
999

Q:

A can complete a piece of work in 12 days, A, B and C can complete the work in 6 days. Efficiency of B is 0.5 times the efficiency of A. In how many days C can complete the work alone?

  • 1
    10 days
  • 2
    16 days
  • 3
    24 days
  • 4
    12 days
  • 5
    None of these
  • Show Answer
  • Workspace

Answer : 3. "24 days"

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today