A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is?
5 929 5efead3cd4461c5b47dce856
Q:
A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is?
- 116 daysfalse
- 210 daysfalse
- 312 daysfalse
- 415 daystrue
- Show Answer
- Workspace
- Discuss