A can do 2% of a work in 4 days, B can do $$33{1\over 3}\%$$ of the same work in 10 days. They worked together for 9 days. C completed the remaining work in 6 days. B and C together will complete 75% of the same work in :

  • 1
    9 days
  • 2
    15 days
  • 3
    10 days
  • 4
    12 days
  • Show Answer
  • Workspace

Answer : 3. "10 days "