A can do a certain job in 12 days. B is 60% more efficient than A. The number of days, it takes B to do the same piece of work is ………5
1103 5bdc5760710b5551ccc2f933
Q: A can do a certain job in 12 days. B is 60% more efficient than A. The number of days, it takes B to do the same piece of work is ………
- 16 daysfalse
- 26 ¼ daysfalse
- 37 ½ daystrue
- 48 daysfalse
- Show Answer
- Workspace
- Discuss