A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid ₹ 960 for the whole work. How much money A gets?
5 841 5f043fccd3626553adad6fd3
Q:
A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid ₹ 960 for the whole work. How much money A gets?
- 1₹ 320false
- 2₹ 400true
- 3₹ 480false
- 4₹ 240false
- Show Answer