A can do a work alone in 30 days. He left after doing half the work. If B alone can complete the entire work in 16 days, then how many days will B take to complete the remaining work?
5 837 5f6d899dec13dd748003a4b9
Q:
A can do a work alone in 30 days. He left after doing half the work. If B alone can complete the entire work in 16 days, then how many days will B take to complete the remaining work?
- 19false
- 26false
- 38true
- 412false
- Show Answer
- Workspace
- Discuss