A can do a work in 9 days, B can do a work in 7 days, C can do a work in 5 days. A works on the first day, B works on the second day and C on the third day respectively that is they work on alternate days. When will they finish the work ?5
939 5b5cc73de4d2b4197774f94d
Q: A can do a work in 9 days, B can do a work in 7 days, C can do a work in 5 days. A works on the first day, B works on the second day and C on the third day respectively that is they work on alternate days. When will they finish the work ?
- 1[7 + (215/345)] daysfalse
- 2[6 + (11/215)] daysfalse
- 3[6 + (261/315)] daystrue
- 4[5 + (112/351)] daysfalse