A can finish a piece of the work in 16 days and B can finish it in 12 days. They worked together for 4 days and then A left. B finished the remaining work. For how many total number of days did B work to finish the work completely?

  • 1
    4
  • 2
    6
  • 3
    9
  • 4
    8
  • Show Answer
  • Workspace

Answer : 3. "9"