A contractor undertakes to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged so that the work may finish in time ?
5 879 5ec7b9059d324637e76e67db
Q:
A contractor undertakes to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged so that the work may finish in time ?
- 150false
- 248false
- 356true
- 464false
- Show Answer
- Workspace
- Discuss