A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one- third of the road in made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
5 1096 5ec71d76112c8637e1b279c0
Q:
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one- third of the road in made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
- 1100false
- 260false
- 350false
- 475true
- Show Answer
- Workspace
- Discuss