A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was done,so he put on 25 extra men. By how much time did he exceed the specific time ?5
2213 5b5cc709e4d2b4197774f2ad
Q: A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was done,so he put on 25 extra men. By how much time did he exceed the specific time ?
- 12 daystrue
- 23 daysfalse
- 34 daysfalse
- 45 daysfalse
- Show Answer
- Workspace
- Discuss