A is 3 times faster than B. If A can finish a work 32 days less than that of B, find the number of days need to finish the work if both are working together?5
1902 5b5cc754e4d2b4197774fb62
Q: A is 3 times faster than B. If A can finish a work 32 days less than that of B, find the number of days need to finish the work if both are working together?
- 112 daystrue
- 224 daysfalse
- 332 daysfalse
- 416 daysfalse
- Show Answer
- Workspace
- Discuss