A is 40% more efficient than C and B is 50% more efficient than A. If A and C together can complete a piece of work in 45 days, then find days taken by A, B & C together to complete 50% of the work?
5 1185 62e0f48655271b350333675c
Q:
A is 40% more efficient than C and B is 50% more efficient than A. If A and C together can complete a piece of work in 45 days, then find days taken by A, B & C together to complete 50% of the work?
- 120 daysfalse
- 224 daystrue
- 326 daysfalse
- 432 daysfalse
- 516 daysfalse