A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job if 6. men leave after working for 6 days?
5 1315 5ef5b36a6306ab2a81aacabd
Q:
A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job if 6. men leave after working for 6 days?
- 112 daysfalse
- 224 daysfalse
- 33 daysfalse
- 46 daystrue
- Show Answer
- Workspace
- Discuss