A particular job can be completed by a team of 10 men in 12 days, The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?
5 1369 5ee1fc042bf4c4044646ad10
Q:
A particular job can be completed by a team of 10 men in 12 days, The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?
- 14 daystrue
- 26 daysfalse
- 39 daysfalse
- 418 daysfalse
- Show Answer
- Workspace
- Discuss