A shopkeeper has a job to print certain number of documents and there are three machines P, Q and R for this job. P can complete the job in 3 days, Q can complete the job in 4 days and R can complete the job in 6 days. How many days the shopkeeper will it take to complete the job if all the machines are used simultaneously ?5
2083 5b5cc758e4d2b4197774fbf4
Q: A shopkeeper has a job to print certain number of documents and there are three machines P, Q and R for this job. P can complete the job in 3 days, Q can complete the job in 4 days and R can complete the job in 6 days. How many days the shopkeeper will it take to complete the job if all the machines are used simultaneously ?
- 14/3 daystrue
- 22 daysfalse
- 33/2 daysfalse
- 44 daysfalse
- Show Answer
- Workspace
- Discuss