Get Started
551

Q:

A work can be completed by 20 men in 50 days. 30 more men join them after 10 days of work. How many days will be saved in completion of the work?

  • 1
    18 days
  • 2
    20 days
  • 3
    24 days
  • 4
    28 days
  • Show Answer
  • Workspace

Answer : 3. "24 days"

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today