A work could be completed in 100 days by some workers. How- ever, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
5 443 6401e2ea86fd4161466d6a1c
Q:
A work could be completed in 100 days by some workers. How- ever, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
- 1100false
- 2110true
- 3180false
- 4144false
- Show Answer
- Workspace
- Discuss