Ajay. Vijay and Sashi can do a piece of work in 20, 40 and 60 days, respectively. In how many days can Ajay do the work if he is assisted by Vijay and Sashi on every fourth day?
5 671 643d15ae1ce944a93ea92c5d
Q:
Ajay. Vijay and Sashi can do a piece of work in 20, 40 and 60 days, respectively. In how many days can Ajay do the work if he is assisted by Vijay and Sashi on every fourth day?
- 115 daysfalse
- 2$${{150\over3}}$$ daystrue
- 312 daysfalse
- 4$${{44\over3}}$$ daysfalse
- Show Answer
- Workspace
- Discuss