Q:

At a construction site, 200 workers were working on a building which is scheduled to end within 250 days. After 30 days, 20 workers leave the job. How many more days will it take to complete the work? 

  • 1
    190 days
  • 2
    186 days
  • 3
    245 days
  • 4
    198 days
  • Show Answer
  • Workspace

Answer : 3. "245 days "