At a construction site, 200 workers were working on a building which is scheduled to end within 250 days. After 30 days, 20 workers leave the job. How many more days will it take to complete the work?
5 651 638f38c39ebad6607ba2e138
Q:
At a construction site, 200 workers were working on a building which is scheduled to end within 250 days. After 30 days, 20 workers leave the job. How many more days will it take to complete the work?
- 1190 daysfalse
- 2186 daysfalse
- 3245 daystrue
- 4198 daysfalse
- Show Answer
- Workspace