Q:

How many workers are required for completing the construction work in 10 days?
 I. 20% of the work can be completed by 8 workers in 8 days
 II. 20 workers can complete the work in 16 days
 III. One-eighth of the work can be completed by 8 workers in 5 days

  • 1
    I and II only
  • 2
    II and III only
  • 3
    I only
  • 4
    III only
  • 5
    Any one of three
  • Show Answer
  • Workspace

Answer : 5. "Any one of three"