If 80 Persons can finish a work in 16 days by working 6 hours a day, the number of hours a day should 64 persons work to finish that same job in 15 days is:
5 918 5f068381b13c2d244ad91bcb
Q:
If 80 Persons can finish a work in 16 days by working 6 hours a day, the number of hours a day should 64 persons work to finish that same job in 15 days is:
- 15 hoursfalse
- 27 hoursfalse
- 38 hourstrue
- 46 hoursfalse
- Show Answer
- Workspace
- Discuss