If A, B and C can complete a piece of work in 6 days. If A can work twice faster than B and thrice faster than C, than the number of days C alone can complete the work is:
5 986 5f4ce8bc82369c1d611043c6
Q:
If A, B and C can complete a piece of work in 6 days. If A can work twice faster than B and thrice faster than C, than the number of days C alone can complete the work is:
- 122false
- 211false
- 344false
- 433true