P can complete a piece of work in thrice the time taken to complete Q and R together. If P and Q together can complete the work in $$ 9{3\over 5} $$ days and R alone complete in 16 days, then find the no of days taken to complete the work by P alone?
5 473 63d292995392140e28f3f19a
Q:
P can complete a piece of work in thrice the time taken to complete Q and R together. If P and Q together can complete the work in $$ 9{3\over 5} $$ days and R alone complete in 16 days, then find the no of days taken to complete the work by P alone?
- 18false
- 212false
- 316false
- 424true
- Show Answer
- Workspace
- Discuss