On a systems development project, Richard needs two programmers. He knows John and Smith were able to create a program in 40 days similar to the one he wants to create on his project. He decides to use 40 days as his estimate. This is an example of what type of estimating?5
895 5b5cc7cce4d2b41977751044
Q: On a systems development project, Richard needs two programmers. He knows John and Smith were able to create a program in 40 days similar to the one he wants to create on his project. He decides to use 40 days as his estimate. This is an example of what type of estimating?
- 1Parametric modelingfalse
- 2Analogoustrue
- 3Rule of thumbfalse
- 4Fixed Ratefalse
- Show Answer