P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?5
2748 5b5cc6c0e4d2b4197774db05
Q: P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?
- 156 daysfalse
- 254 daysfalse
- 360 daysfalse
- 464 daystrue
- Show Answer
- Workspace
- Discuss