P can complete a piece of work in thrice the time taken to complete Q and R together. If P and Q together can complete the work in 9 3/5 days and R alone complete in 16 days, then find the no of days taken to complete the work by P alone?
5 645 62f36e1c55c5be58410dc2e8
Q:
P can complete a piece of work in thrice the time taken to complete Q and R together. If P and Q together can complete the work in 9 3/5 days and R alone complete in 16 days, then find the no of days taken to complete the work by P alone?
- 18false
- 212false
- 316false
- 424true
- 515false