P can do a task in 30 days, Q is 50% more efficient than P, R can do the same work in 10 days less than Q if R and Q start task together and after X days they left the task and P completed the remaining task in (X + 8) days. then find the value of X?

  • 1
    2
  • 2
    4
  • 3
    5
  • 4
    8
  • 5
    6
  • Show Answer
  • Workspace

Answer : 2. "4"