P1 alone can do $${2\over 3}$$ of the work in 8 days. P2 alone can do $${7\over 12}$$ of the work in 14 days. P3 alone can do $${8\over 15}$$ of the work in 16 days. In how many days can they complete the work, if all three work together?
5 495 642d2ddc08ca2357ae7e0f98
Q:
P1 alone can do $${2\over 3}$$ of the work in 8 days. P2 alone can do $${7\over 12}$$ of the work in 14 days. P3 alone can do $${8\over 15}$$ of the work in 16 days. In how many days can they complete the work, if all three work together?
- 1$${60\over 19}$$ daysfalse
- 2$${120\over 9}$$ daystrue
- 3$${100\over 17}$$ daysfalse
- 4$${80\over 17}$$ daysfalse
- Show Answer
- Workspace
- Discuss