Q: Planning Process Group What are the Project Management Processes included in the Planning Process Group?

  • Show Answer
  • Workspace

Answer :
Explanation :

Develop Project Management Plan Scope Planning Scope Definition Create WBS Activity Definition Activity Sequencing Activity Resource Estimating Activity Duration Estimating Schedule Development Cost Estimating Cost Budgeting Quality Planning Human Resource Planning Communications Planning Risk Management Planning Risk Identification Qualitative Risk Analysis Quantitative Risk Analysis Risk Response Planning Plan purchases and Acquisitions Plan Contracting