Q: Project Communications Management - Processes Describe the Inputs, Tools and Techniques , Outputs included in the Communications planning?

  • Show Answer
  • Workspace

Answer :
Explanation :

I. Inputs Enterprise environmental factors Organizational process assets Project scope statement Project management plan                    - Constraints                    - Assumptions II. Tools and Techniques Communications requirements analysis Communications technology III. Outputs Communications management plan