Q: Project Integration Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Direct and Manage Project Execution Phase?

  • Show Answer
  • Workspace

Answer :
Explanation :

I. Inputs Project management plan Approved corrective actions Approved preventive actions Approved change requests Approved defect repair Validated defect repair Administrative closure procedure II. Tools and Techniques Project management methodology Project management information system III. Outputs Deliverables Requested changes Implemented change requests Implemented corrective actions Implemented preventive actions Implemented defect repair Work performance information