Q: Project Time Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Activity Definition ?

  • Show Answer
  • Workspace

Answer :
Explanation :

I. Inputs Enterprise environmental factors Organizational process assets Project scope statement Work breakdown structure WBS dictionary Project management plan II. Tools and Techniques Decomposition Templates Rolling wave planning Expert judgment Planning component III. Outputs Activity list Activity attributes Milestone list Requested changes