Raju, Shobha and Mohan can do a work in 15 days, 20 days and 25 days respectively. In how many days, will the work be finished, if they do it on alternate days?
5 1194 64805a0f51bf194753036c9f
Q:
Raju, Shobha and Mohan can do a work in 15 days, 20 days and 25 days respectively. In how many days, will the work be finished, if they do it on alternate days?
- 1$$15{9\over 10}$$ daysfalse
- 2$$18{7\over 10}$$ daysfalse
- 3$$21{7\over 10}$$ daysfalse
- 4$$18{9\over 10}$$ daystrue
- Show Answer