Q:

Raju, Shobha and Mohan can do a work in 15 days, 20 days and 25 days respectively. In how many days, will the work be finished, if they do it on alternate days?

  • 1
    $$15{9\over 10}$$ days
  • 2
    $$18{7\over 10}$$ days
  • 3
    $$21{7\over 10}$$ days
  • 4
    $$18{9\over 10}$$ days
  • Show Answer
  • Workspace

Answer : 4. "$$18{9\over 10}$$ days"